Projects 2025.
-
Viktor Lenac Shipyard, Croatia
(shipyard)
Project description:
Electrical installation services on vessels:
-
AL MIRQAB
TS37001/Add01
- opening/closing Roxtec cable glands /existing/- 4 pcs.
LSB PANEL 2 - disconnecting old existing cables/cable 1 x 25 mm2 - 5 pcs.
- installing 5 new cables 1 x 25 mm2/.... /along the existing cable route/from the LSB Panel 2 electrical cabinet - to the new position of the Harmonics Filter electrical cabinet ..... 5 cables x 20 meters = 100 meters
- bundling the installed cable/along the existing cable route/
- connecting the cable to the Backup switch in Panel 2
LSB PANEL 3 - disconnecting old existing cables /cable 5 x 1.5 mm2 - 2 pcs.
- installing 2 new cables 5 x 1.5 mm2 /along the existing cable route from the LSB Panel 3 electrical cabinet - to the new position of the cabinet Harmonics Filter..... 2 cables x 20 meters = 40 meters
- routing of the installed cable / along the existing cable route /
- connecting the cable at the Position in the electrical cabinet LSB Panel 3
TS38001/Add04
- electrical work on removing old grout and filling pipes with new waterproof grout due to leaks on board
/Farsounder pipe cable and Underwater Light cable/bow position/through ballast tank no. 1/
Duration of works: January 2025.
-
ARTEMIS
- electrical installation services
TS 37001 - BTU - ENG 020
- replacement and wiring of automatic fuses / 16 A / - 2 pcs., in the wheelhouse control panel
- dismantling of the existing fuse protection panel
- disconnection and dismantling of old fuses
- installation, connection of new fuses
- if necessary, adjustment (expansion) of the fuse protection panel
TS 41010 - BTU ENG 013
- relocation of electrical components from the old electrical cabinet (from the osmosis system that was dismantled on the ship) to the new electrical cabinet (for starting the newly installed STERN TUBE lubrication pump), wiring according to the electrical diagram
Duration of works: January 2025. - February 2025.
-
ATHENA
- electrical installation services
TS 37001 - BTU - ENG 020
- replacement and wiring of automatic fuses / 16 A / - 2 pcs., in the wheelhouse control panel
- dismantling of the existing fuse protection panel
- disconnection and dismantling of old fuses
- installation, connection of new fuses
- if necessary, adjustment (expansion) of the fuse protection panel
TS 41010 - BTU ENG 013
- relocation of electrical components from the old electrical cabinet (from the osmosis system that was dismantled on the ship) to the new electrical cabinet (for starting the newly installed STERN TUBE lubrication pump), wiring according to the electrical diagram
Duration of works: January 2025. - February 2025.
Project description:
Electrical installation services on vessels:
DALMACIJA
KORČULA
JURAJ DALMATINAC
ATHENA
ARTEMIS
USS HERSHEL WOODY WILLIAMS
AL MIRQAB
USNS BRUCE C HEEZEN
BREB CUXHAVEN
JAGUAR
SPRITZ
KIJAC
VERVECE
MSC ALIX 3
LOŠINJ
MARKO POLO
MARJAN
GREEN SPINEL
RED OPAL
Description of works:
- construction of cable trays
- inserting cables according to schemes
- maintenance and inspection of equipment
- marking all cores and cables with the appropriate marking
Project duration: January 2025. - currently
-
3. MAJ Shipyard JSC, Croatia
(shipyard)
NEW CONSTRUCTION - 527
Self-unloading ship for the transport of bulk cargo - very specific because it was designed for the needs of the original customer - Canadian Algoma and navigation on the North American Great Lakes
Project description:
- according to the defined blueprints and list of materials - laying and bracing all the cables, mounting all the devices, inserting and connecting the cables to the electrical appliances, cargo space fans, lighting, lighting distributors and fire alarm
- mark all wires and cables with appropriate markings
- take all devices.
- test the functionality of the lighting
- mount nameplates and hand over the necessary programs to the shipowner and the registry
- planned tasks include daily cleaning of the space from excess built-in material and maintaining the orderliness of the space itself
Duration of the works: January 2025. - currently
-
INA d.o.o., Croatia
(production, storage and logistics of propene and propane in Rijeka oil refinery)
Project description:
- electrical installation works on the project "BHRK371 Residue Upgrade Program of the Rijeka Refinery
Project duration: January 2025. - currently

-
Saint-Martin-de-Gurson, France
SOURCE ALMA ST MEDARD
(mineral water manufacturer)
Project description:
- installation of air conveyors
- electrical installation works
Project duration: January 2025.
-
Ardenay-sur-Merize, France
SOURCE ALMA CRISTAL ROC
(mineral water manufacturer)
Project description:
- installation of air conveyors
- electrical installation works
Project duration: January 2025. - February 2025.
-
Grigny, France
COCA-COLA EUROPACIFIC PARTNERS FRANCE
(production and distribution of Coca-Cola and other soft drinks)
Project description:
- electrical installation work
- assembly of cabel channels, conecting cabels
- connecting cabinets
Project duration: February 2025. - March 2025.
-
Glasgow, UK
COCA-COLA EUROPACIFIC PARTNERS
(production and distribution of Coca-Cola and other soft drinks)
Project description:
- dismantling of the production line
Project duration: January 2024.
-
Bradford, UK
PRINCES LIMITED
(food and beverages manufacturer)
Project description:
- assembly of the previously dismantled production line
- electrical installation works
Project duration: February 2024. - March 2024.
-
La Tremblade, France
BURG VINAIGRES SAS
(vinegar and alcoholic beverages manufacturer)
Project description:
- assembly of the production line
- electrical installation works
- assembly of cabel channels, connecting cabels
Project duration: February 2025. - March 2025.
-
Tonquédec, France
BRASSERIE RÉGIONALE DE L'OUEST - COZIGOU
(beer manufacturer)
Project description:
- assembly of the production line
- electrical installation works
- assembly of cabel channels, connecting cabels
Project duration: March 2025.