Projects 2024.
-
Viktor Lenac Shipyard, Croatia
(shipyard)
Project description:
Electrical installation services on vessels:
-
MSC AZURIT F
Installation of BWTS system according to the delivered documentation:
- locksmith works on the production and assembly: foundations of electrical equipment, cable passages and cable routes
- assembly of electrical equipment, installation of switches (if necessary, modification of copper busbars and joints and adjustment of door openings)
- assembly and connection of cables, final megger test
- handover of electrical works to the OKK department and the shipowner's representative (assembly and installation)
- assistance to the service technician during testing and commissioning of the system
- delivery of complete material for temporary and final cable connection, connection and marking of cables
Duration of works: October 2023. - January 2024.
-
DIEGO
Installation of BWTS system according to the delivered documentation:
- locksmith works on the production and assembly: foundations of electrical equipment, cable passages and cable routes
- assembly of electrical equipment, installation of switches (if necessary, modification of copper busbars and connections and adjustment of door openings)
- assembly and connection of cables, final megger test
- handover of electrical works to the OKK department and the shipowner's representative (assembly and installation)
- assistance to the service technician during testing and commissioning of the system
Duration of works: June 2024. - July 2024.
-
AMAZONITH
Installation of BWTS system according to the delivered documentation:
- locksmith works on the production and assembly: foundations of electrical equipment, cable passages and cable routes
- assembly of electrical equipment, installation of switches (if necessary, modification of copper busbars and connections and adjustment of openings in the GRP doors)
- assembly and connection of cables, final megger test
- handover of electrical works to the OKK department and the shipowner's representative (assembly and installation)
- assistance to the service technician during testing and commissioning of the system
Duration of works: July 2024. - August 2024.
-
BREB COURAGEOUS
Installation of BWTS system according to the delivered documentation:
- locksmith works on the production and assembly: foundations of electrical equipment, cable passages and cable routes
- assembly of electrical equipment, installation of switches (if necessary, modification of copper busbars and connections and adjustment of openings in the GRP doors)
- assembly and connection of cables, final megger test
- handover of electrical works to the OKK department and the shipowner's representative (assembly and installation)
- assistance to the service technician during testing and commissioning of the system
Duration of works: August 2024.
-
BREB COURTESY
Installation of BWTS system according to the delivered documentation:
- installation of electrical equipment, installation of switches (if necessary, modification of copper busbars and connections and adjustment of openings in the GRP doors)
- installation and connection of cables, final megger test
- handover of electrical works to the OKK department and the shipowner's representative (assembly and installation)
- assistance to the service technician during testing and commissioning of the system
Duration of works: September 2024. - October 2024.
Project description:
Electrical installation services on vessels:
LIBURNIA
FAROS
ILOVIK
HERMES
MAS
USNS YUMA
DANAVIK
MSC AZURIT F
DOBRA
ČETIRI ZVONIKA
FALESIA
KORČULA
USS HERSHEL WOODY WILLIAMS
VELA LUKA EX HERMES
PETAR HEKTOROVIĆ
SEPEN
VALUN
USNS TRENTON
GNV ALLEGRA
THERASIA M
SVETI DUJE
BOL
DIEGO
ASSO VENTIQUATTRO
ETRUSCO
AMAZONITH
SAND CARRIER 103
SAND CARRIER 105
ZAPPHIRE
SVETI VID
BREB COURAGEOUS
KINGFISHER
BUZZARD
EMERALD
SAND CARRIER 104
SAND CARRIER 106
BLACKBIRD
WIND SPIRIT
FIUME
AL MIRQAB
BREB COURTESY
PRINCE ABDULAZIZ
DALMACIJA
KRK
ODOARDO AMORETTI
USS INDIANAPOLIS
ASSO VENTOTTO
BREB CUXHAVEN
IEVOLI BLUE
LANGE WAPPER
BBC ALBERTA
Description of works:
- construction of cable trays
- inserting cables according to schemes
- maintenance and inspection of equipment
- marking all cores and cables with the appropriate marking
Project duration: January 2024. - December 2024.
-
3. MAJ Shipyard JSC
(shipyard)
NEW CONSTRUCTION - 527
Self-unloading ship for the transport of bulk cargo - very specific because it was designed for the needs of the original customer - Canadian Algoma and navigation on the North American Great Lakes
Project description:
- according to the defined blueprints and list of materials - laying and bracing all the cables, mounting all the devices, inserting and connecting the cables to the electrical appliances, cargo space fans, lighting, lighting distributors and fire alarm
- mark all wires and cables with appropriate markings
- take all devices.
- test the functionality of the lighting
- mount nameplates and hand over the necessary programs to the shipowner and the registry
- planned tasks include daily cleaning of the space from excess built-in material and maintaining the orderliness of the space itself
Duration of works: January 2024. - December 2024.
-
INA d.o.o., Croatia
(production, storage and logistics of propene and propane in Rijeka oil refinery)
Project description:
- electrical installation works on the PROPANE / PROPYLENE SPLITTER project (PPS U-391 and PPS TANK SPACE U-335 I INTERCONNECTING)
Work description:
- electro-instrumentation works
Project duration: March 2024. - August 2024.
Project description:
- electrical installation works on the Project for the reconstruction of HCU and SRU facilities as part of the Heavy Waste Processing Program in Rijeka Oil Refinery (RUP) in the Rijeka Oil Refinery
Work description:
- disassembly and assembly of electro-instrumentation equipment on
burner 379-X-201
Project duration: December 2024.
-
Almaty, Kazakhstan
CARLSBERG KAZAKHSTAN LTD
(beer manufacturer)
Project description:
- electrical installation works - installation of a complete bottling line
Project duration: January 2024. - March 2024.
-
Biskirchen, Germany
RADEBERGER GRUPPE - SELTERS MINERALQUELLE
(beer manufacturer)
Project description:
- electrical installation works - assembly of cabel channels, connecting cabels
Project duration: January 2024. - February 2024.
-
Nissan Lez Enserune, France
REFRESCO SITE DE NISSAN
(producer of soft drinks, water, fruit juices, energy drinks, alcohol, and plant-based drinks)
Project description:
- dismantling of the production line
Project duration: January 2024. - February 2024.
-
Marges, France
REFRESCO FRANCE SAS
(producer of soft drinks, water, fruit juices, energy drinks, alcohol, and plant-based drinks)
Project description:
- assembly of the previously dismantled production line
Project duration: February 2024. - April 2024.
-
Laqueuille, France
AQUAMARK LAQUEUILLE
(manufacturer of soft bevergaes and mineral water)
Project description:
- assembly of the production line
- electrical installation works
Project duration: January 2024. - February 2024.
-
Obernai, France
BRASSERIE KRONENBOURG
(beer manufacturer)
Project description:
- assembly of the production line
- electrical installation works
Project duration: February 2024.
-
Ravena, Italy / Altinova, Turkey
Ship ADRIA MARINA
Project description:
- upgrade of the automation
- cable pulling
- inserting cables according to schemes
- marking all cores and cables with the appropriate marking
Project duration: January 2024. - March 2024.
-
Artenay, France
TEREOS SUCRE FRANCE ARTENAY
(sugar manufacturer)
Project description:
- assembly of the production line
- electrical installation works
Project duration: March 2024.
-
Obernai, France
BRASSERIE KRONENBOURG
(beer manufacturer)
Project description:
- assembly of the production line
- electrical installation works
Project duration: March 2024.
-
Saint-Diéry, France
AQUAMARK ST DIERY
(mineral water manufacturer)
Project description:
- assembly of the production line
- electrical installation works
Project duration: March 2024.
-
Trieste, Italy
FINCANTIERI S.P.A. shipyard
M/v SILVERSEA SILVER WHISPER
Project description:
- led lighting installation
- dismounting activity of old light fixtures as downlights, spotlight, HV linear fluorescent and incandescent bulbs
- dismounting activity of old power supply or voltage transformer I
- cabling of new power supplies and cabling of 20 cm cable from power supply to light fixtures
- equipment installation and functional tests
Project duration: April 2024. - May 2024.
-
Ajdovščina, Slovenia
INCOM D.O.O.
(ice cream and chocolate producer)
Project description:
- assembly of the production line
- electrical installation works
Project duration: April 2024.
-
Champigneulles, France
BRASSERIES CHAMPIGNEULLES
(beer manufacturer)
Project description:
- assembly of the production line
- electrical installation works
Project duration: May 2024.
-
Meyras, France
LES SOURCES DU PESTRIN
(mineral water manufacturer)
Project description:
- assembly of the production line
- electrical installation works
Project duration: May 2024. - June 2024.
-
Bad Neuenahr-Ahrweiler, Germany
COCA-COLA EUROPACIFIC PARTNERS
(production and distribution of Coca-Cola and other soft drinks)
Project description:
- electrical installation works
- connection works
Project duration: June 2024. - July 2024.
-
Monterrey, Mexico
BEBIDAS MUNDIALES
(beverage, soft drinks manufacturer)
Project description:
- electrical assembly support
- connecting ergoblocks
- electrical installation works
Project duration: July 2024. - August 2024.
-
London, UK
COCA-COLA EUROPACIFIC PARTNERS
(production and distribution of Coca-Cola and other soft drinks)
Project description:
- dismantling of the production line
Project duration: July 2024. - August 2024.
-
Bradford, UK
PRINCES LIMITED
(food and beverages manufacturer)
Project description:
- assembly of the previously dismantled production line
- electrical installation works
Project duration: August 2024. - September 2024.
-
Neutraubling, Germany
KRONES AG
(packaging and bottling machine manufacturer)
Project description:
- rewiring switch cabinets
- electrical installation works
Project duration: July 2024. - August 2024.
-
Weiterstadt, Germany
RIEDBETON GMBH
(production and distribution of concrete products)
Project description:
- wiring switch cabinets
- electrical installation works - assembly of cabel channels, connecting cabels
Project duration: August 2024. - November 2024.
-
Saint-Alban-les-Eaux, France
REFRESCO MINERAL WATER ST ALBAN LES EAUX
(mineral water manufacturer)
Project description:
- assembly of the production line
- electrical installation works
- assembly of cabel channels, connecting cabels
Project duration: September 2024. - November 2024.
-
Kansas city, USA
HEARTLAND COCA-COLA
(production and distribution of beverages)
Project description:
- assembly of the production line
- electrical installation works
- assembly of cabel channels, connecting cabels
Project duration: October 2024. - December 2024.
-
Bremen, Germany
SATURN PETCARE
(pet food manufacturer)
Project description:
- reconnection of existing cables
- mounting cable trays
- electrical installation works
Project duration: October 2024.
-
Amt Wachsenburg, Germany
BORN SENF & FEINKOST GMBH
(food manufacturer)
Project description:
- assembly of the production line
- mounting cable trays
- electrical installation works - assembly of cabel channels, connecting cabels
Project duration: November 2024.
-
Konya, Turkey
SERIOPLAST AMBALAJ SAN.TIC. A. Ş.
(producer of rigid plastic packaging)
Project description:
- installation, commissioning, maintenance and overhaul of machinery and installations for the bottling production line
- electrical installation works - mounting cable trays, assembly of cabel channels, connecting cabels
Project duration: November 2024.
-
Bremerhawen, Germany
SHIP MANARA
Project description:
- cable pulling
- connecting cabinets
- inserting cables according to schemes
- marking all cores and cables with the appropriate marking
Project duration: November 2024. - December 2024.
-
Berlin, Germany
RADEBERGER GRUPPE KG
(beer manufacturer)
Project description:
- assembly of the production line
- electrical installation works
- assembly of cabel channels, connecting cabels
Project duration: November 2024. - December 2024.
-
Löhnberg, Germany
RADEBERGER GRUPPE - SELTERS MINERALQUELLE
(mineral water manufacturer)
Project description:
- installation of lighting in a hall
Project duration: December 2024.